Wednesday, October 31, 2012

another day of drywalling

last of the gas meters being installed

Tuesday, October 30, 2012

today's crew

a day of drywalling

the power has been connected

Monday, October 29, 2012

taking the plastic off the curbs

more trim

putting in the water lines

Friday, October 26, 2012

preparing for the curbs

the start of the pour

taking down the scaffolding

today's crew from RBC

insulation time

installing the baseboards

Thursday, October 25, 2012

Wednesday, October 24, 2012

today's crew

another rainy day so inside work was done


door trim

window trim


moving the shed again

getting ready for curbs

Tuesday, October 23, 2012

a rainy day so all work was inside

installing doors

waiting to cut some trim

installing some baseboards

installing the drywall

puttying the nail holes

Monday, October 22, 2012

front dormers are done and the scaffoliding is down

working on the back dormer

getting ready for the curbs

Friday, October 19, 2012

putting in the refuse containers

putting in pipe for the cable for the streetlight

closing up the trenches

the siding crew

installing the doors

Wednesday, October 17, 2012

taking down the scaffolding

getting ready for the soffit

digging a trench for the hydro wires

installing the doors

getting ready for some curbs

Tuesday, October 16, 2012

poring the porches

closing in the gables

more siding

shingling should be done today